Petone to Melling Walkway and Cycleway. This project involved installing CFA concrete piles as night works within meters of vital railway network infrastructure. These works were completed at night and involved high accuracy dimension and location install of No. 194 500mm dia 4.1-7.9m deep soft piles and No. 194 500mm dia 4.1-7.9m deep Hard Piles. Work was completed with Moore Constructions GEAX EK110 Piling Rig and skilled operations staff. Concrete supply by main contractor Fulton Hogan.