Toms Creek Bridge – Queenstown

Design & Build Precast Bridge — Luxury Resort Infrastructure

Span

12m

Beams

3 Units

Beam Weight

15T+

Piles

3 Bored

Delivery

Design & Build

Project Overview

Moore Construction delivered the design and build of the Toms Creek Bridge for the Gibbston Valley Resort development, providing critical access to a high-end tourism destination in Queenstown.

The project required a fully integrated approach combining design, precast manufacturing, piling, and installation within a premium and environmentally sensitive setting.

Engineering Solution

The bridge structure consists of three pre-stressed Double T beams, forming a 12-metre span across Toms Creek.

Each beam measures 725mm deep by 2000mm wide and weighs in excess of 15 tonnes, with approximately 360 tonnes of pre-stressing applied to achieve the required strength for heavy vehicle loading.

The system is supported by cast in-situ abutments founded on 600mm diameter bored piles, providing a robust and durable foundation solution.

Precast Manufacturing

The bridge beams were manufactured off-site in collaboration with Hi-Stress Concrete, allowing for high quality control and efficient project delivery.

  • Pre-stressed Double T beam fabrication
  • Off-site production for improved quality and efficiency
  • Prefabricated kerb boxing for rapid installation
  • Use of temporary mould systems to streamline production

Construction Delivery

Bridge beams were installed using Moore Construction’s 80-tonne crawler crane, carefully coordinated to ensure safe lifting and precise placement onto the abutments.

  • Heavy lifting of 15+ tonne precast beams
  • Precision placement onto abutments
  • Grouted shear keys forming a continuous deck
  • Formation of a 6m wide bridge deck

Project Challenges

  • Construction within a premium resort environment
  • Coordination of precast and in-situ works
  • Heavy lifting and precise placement of structural elements
  • Maintaining programme efficiency within a constrained site

Outcome

The completed bridge provides a durable and high-capacity access solution for the Gibbston Valley Resort, capable of supporting heavy construction and operational traffic.

    Project Gallery

Key Capabilities Demonstrated

  • Design and build bridge delivery
  • Precast and pre-stressed concrete systems
  • Bored pile foundation construction
  • Heavy lifting and installation engineering
  • Integration of manufacturing and construction
  • Delivery in premium development environments